摘要
结合示范性武威兆瓦级荒漠光伏并网电站的建设,介绍了该光伏电站的设计理念、系统构成及运行情况,分析讨论了有关技术原则和运行数据,指出在我国西部地区采用跟踪支架方式是有益的,并要充分考虑电站组件的清洗问题。
Based on construction of a demonstration megawatt-class solar photovoltaic grid-connected power plant built in desert areas of Wuwei,an introduction is presented to its design concept,system configuration and operational conditions.By analyzing relevant technical rules and operational data,it is believed to be profitable to adopt solar energy directional tracing bracket in western area of China,in which case cleaning problems of relevant power plant components should be considered carefully.
出处
《发电设备》
2011年第2期134-136,143,共4页
Power Equipment
基金
国家科技部"十一五"国家高技术研究发展计划(863计划)项目资助
关键词
太阳能
光伏发电系统
并网
跟踪系统
发电量分析
solar energy
photovoltaic power generation system
grid connection
tracing system