复杂桩端持力层条件下钻孔桩施工质量控制要点 被引量:4

CONSTRUCTION OF BORED PILE IN ENVIRONMENT OF COMPLEX PILE BEARING LAYERS
下载PDF
导出
摘要 针对杭州地区某工程场地内3种差异明显的中风化持力层,设计了3种不同的工程试桩类型,在6根试桩施工过程中,从入岩界面的判断、岩样的判定、钻杆进尺速度和入岩总时间几个关键环节分别制定操作性较强的控制标准,从项目实际运作情况看,桩基安全性、进度、造价和管理科学合理。 Three pile testing programs, for different length of pile,different pile bearing layers and the status of rock-socketed piles,are designed,aim at three significant different medium weathered siltstone pile bearing layers on a construction site in Hangzhou. In the construction of six test pile in different bearing layers, we developed a strong operational control standards judging from some key aspects like the judgments of rock embedding interface and rock samples,speed of drill pipe and total time of rock embedding. Based on the actual operation of the project,the pile safety,construction schedule,cost and management are scientific and rational.
出处 《建筑技术》 北大核心 2011年第3期275-277,共3页 Architecture Technology
基金 浙江省建设厅[2010]166号
关键词 持力层 静载试验 单桩承载力 入岩 bearing layer static load test bearing capacity of single pile rock embedding
  • 相关文献

参考文献2

二级参考文献8

共引文献9

同被引文献11

引证文献4

二级引证文献16

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部