摘要
分析了珊溪水电厂原监控系统及改造原因,阐述了监控升级改造的设计原则、施工调试方案以及改造后的监控系统结构。改造后的系统已应用在珊溪电厂,效果表明该方案的工程有效性。
The condition of Shanxi hydropower plant's former supervisory control system(SCS) and the reasons for its upgrading and modernization are analyzed.Then the principle for upgrading and modernization of former SCS are explained.Finally,the current condition of SCS after modernization is introduced.Now,the upgraded and modernized SCS has already been applied in the Shanxi hydropower plant successfully.The modernization fully met the purposes such as improving system reliability,enhancing system functions and optimizing system structure.
出处
《水电自动化与大坝监测》
2011年第1期14-16,共3页
HYDROPOWER AUTOMATION AND DAM MONITORING
关键词
水电厂
计算机监控系统
网络调试
无人值班(少人值守)
hydroelectric power plant
supervisory control system
network commissioning
unmanned shift