液压爬升模板技术在保利V座大厦工程中的应用 被引量:10

Application of Hydraulic Climbing Formwork Technology in Poly V Building
下载PDF
导出
摘要 保利V座大厦主楼为钢框架-钢筋混凝土核心筒结构,平面呈椭圆形。核心筒内外墙体采用全自动液压爬升模板技术与立体交叉式施工工艺相结合的施工方法,筒体竖向结构在不分流水段的情况下最快达到平均1层/2.5d的施工速度。结合具体工程实例,介绍了液压自动爬升模板的整体刚度大、密闭性好、操作方便、爬升速度快等特性;阐述了液压爬升模板系统的安装、爬升、拆卸等施工工艺,同时也分析了模板爬升及使用过程中的质量保证措施。 Poly V building is designed as elliptical plan with steel frame and reinforced concrete core tube structure. Combination methods of automatic hydraulic climbing formwork and alternated construction technology are adopted in the core tube wall construction. The average construction speed can reach 2.5 days per layer without dividing construction segment. Combining with concrete project, the authors introduce main characteristics of high integral rigidity, favorable leak tightness, convenient operation and fast climbing speed. Then they describe construction technology about system installation, climbing and dismantling of hydraulic self-climbing formwork, but also analyze the process of climbing and the quality assurance measures.
出处 《施工技术》 CAS 北大核心 2011年第3期66-68,81,共4页 Construction Technology
关键词 超高层建筑 核心筒 液压爬升模板 super high-rise building core tube hydraulic climbing formwork
  • 相关文献

参考文献7

二级参考文献20

  • 1王升磊.集群液压爬升模板施工实例论述[J].建筑安全,2005,20(9):42-45. 被引量:1
  • 2张良杰.莫斯科联邦大厦墙柱液压爬升模板施工技术[J].施工技术,2007,36(2):26-29. 被引量:5
  • 3.GB50017-2003钢结构设计规范[S].北京:中国计划出版社,2003..
  • 4GB50204-2002.混凝土结构工程施工质量验收规范[S].[S].,2002..
  • 5GB50054-95低压配电设计规范[S].北京:中国计划出版社,1995.
  • 6北京土木建筑协会.模板与脚手架工程施工技术措施[M].北京:经济科学出版社,2005:103-104.
  • 7JGJ183-2009液压升降整体脚手架安全技术规程[S].北京:中国建筑工业出版社,2009.
  • 8北京市建筑工程研究院.Q/BCJ03-2001建筑施工分体式附着升降脚手架[S].北京,2001.
  • 9A,H.拉耶夫斯基.结构稳定计算原理[M].赵超燮,袁耀明译.北京:高等教育出版社,1966.
  • 10JGJ128-2000建筑施工门式钢管脚手架安全技术规范[S].北京:中国建筑工业出版社,2000.

共引文献40

同被引文献35

引证文献10

二级引证文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部