摘要
论文针对上海地铁2号线工程,采用三维数值模拟软件FLAC3D对盾构隧道开挖后壁后注浆对地表沉降影响进行了模拟计算与实测数据的对比分析研究.研究揭示了注浆长期强度和注浆浆液时间-强度变化对地表沉降的影响规律,所得结论可供盾构隧道设计与施工参考使用.
For the Shanghai Metro Line 2 project,using three-dimensional numerical simulation software FLAC3D the im-pact of surface subsidence of the shield tunnel excavation and the posterior grouting was simulated and comparatively anal-yzed with measured data.Research reveals the law of surface subsidence for the long-term strength and grouting time-in-tensity change.The conclusion could be used and referenced for the design and construction of shield tunnel.
出处
《河北工业大学学报》
CAS
北大核心
2011年第1期110-113,共4页
Journal of Hebei University of Technology
关键词
盾构施工
壁后注浆
地表沉降
数值模拟
shield construction
wall grouting
surface subsidence
numerical simulation