摘要
根据华润徐州电厂三期工程机组调试的实际情况,详细介绍了上汽1000MW超超临界汽轮机设计特点及运行情况,并对机组启动调试过程中出现的一些问题做了简要分析。该机组的成功投运对以后此类大型汽轮机的启动调试具有一定的指导意义。
According to the commissioning situation of the unit in 3rd phase project of Huarun Xuzhou Power Plant,the article detailedly introduces the design features and operation of Shanghai's 1000MW USC steam turbine and also analyzes some problems appeared in the process of start-up control and commissioning.So,it can be regarded as a good example for the commencement and commissioning of large capacity turbines.
出处
《热力透平》
2011年第1期50-53,共4页
Thermal Turbine