摘要
一闸首及其基础是三峡船闸渗流监测的关键部位。通过对三峡3个蓄水阶段中得到的永久船闸基础廊道内渗流监测资料进行分析,了解一闸首及其基础的渗流特性;分析并发现影响基础地下水位及渗流量的主要因素,建立典型测压管水位和渗流量统计模型。
Lock head No.1 and its foundation are the key parts of TGP ship lock seepage monitoring;By analysis seepage monitoring data obtained from foundation-gallery in ship lock of three-phases reservoir water level hoist,find out seepage characteristic of lock head No.1 and its foundation;analyse and find out main effectible factors of underground water level and seepage,set up statistical models on typical piezometric tube level and seepage.
出处
《水利科技与经济》
2011年第2期14-17,共4页
Water Conservancy Science and Technology and Economy
基金
河海大学水文水资源与水利工程科学国家重点实验室专项基金(2009586012)
关键词
三峡蓄水
船闸闸首
渗流监测
TGP impoundment
permanent ship lock head
seepage monitoring