通过古城水电站防渗墙部分施工过程,探讨了在基岩、特大孤石层及破碎带的钻爆施工方法、控制重点及应急情况的处理方法。
This paper investigated the drilling and blasting method used in bedrock,large boulders and broken layers,control points and the emergency situation handling during the construction of cut-off wall of Gucheng Hydropower station.
出处
《水电与新能源》
2011年第2期51-53,共3页
Hydropower and New Energy
关键词
防渗墙
钻孔
灌浆
聚能爆破
cut-off wall
drilling
grouting
energy cumulative blasting