桥跨箱梁混凝土浇筑次序的优化研究 被引量:2

Optimizing Procedures for Concrete Cast Box-Shaped Girders of Bridge Superstructure
下载PDF
导出
摘要 通过邹平西外环路桥工程雪花山庄大桥现浇箱梁及青岛流亭机场高架桥等实践及梁体应力分析,提出箱梁混凝土浇筑次序的优化方案,即先浇筑底板及腹板,后浇筑顶板及翼板.其优点有:内模支撑简单;节省人工及材料费;第一次浇筑混凝土后形成的结构抵抗地基不均匀沉降等风险的能力大大增强;施工质量可控性好. Based on the practice and beam stress analysis of the cast-in-place box-girder of Xuehuashanzhuang Bridge and Liuting Airport Viaduct in Qingdao,an optimized sequence of box-shaped girder's casting that the bottom slab and web are to be cast first and the deck and wing slabs second is put forward in this paper.Its advantages go as follows:the inside formworks are simple,the labor and materials are economized,the ability of sustaining subsidence asymmetry is strengthened and the quality controllability of the construction is good.
作者 张师定
出处 《青岛理工大学学报》 CAS 2010年第6期10-13,共4页 Journal of Qingdao University of Technology
关键词 桥梁施工 桥跨箱梁 混凝土浇筑 bridge construction box-girder of bridge superstructure cast of concrete
  • 相关文献

参考文献2

  • 1JTJ 041-2000,公路桥涵施工技术规范[S].北京:人民交通出版社,2000.
  • 2宋德昌,郑纪伟,周学军,等.现浇预应力混凝土连续箱梁满堂支架施工工法[G]//中国公路建设行业协会.公路工程工法汇编(2009).北京:人民交通出版社,2010.

共引文献3

同被引文献3

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部