摘要 中国碾压混凝土坝建设始于80 年代中期。1986 年从第1 座坑口碾压混凝土坝完成后,10 多年来已竣工28 座, 在建的有15 座, 合计43 座, 居世界之首, 还有21 座正在设计中。在设计、科研、施工实践中, 碾压混凝土筑坝技术有所发展, 有所进步。通过运行证实, 这些成熟的经验将对下一世纪继续发展碾压混凝土坝有指导和推动作用。即将开工兴建的龙滩水电站一期工程大坝高192 m , 将是世界上最高的碾压混凝土重力坝。 The construction of RCC dam in China started in the middle period of 1980s. The first RCC dam in China was completed in Kengkou in 1986. Since then, 28 RCC dams have been completed, 15 such dams under construction and 21 such dams under design. The completed and under construction RCC dams in total in China are 43, which stands in the forefront of that in the world. Through design, scientific study and construction practice, the RCC dam construction technology has made the development and progress to certain extent.
作者 沈崇刚
机构地区 中国大坝委员会
出处 《水力发电》 北大核心 1999年第10期41-44,共4页 Water Power
关键词 碾压混凝土坝 筑坝技术研究 设计 施工工艺 运行经验 RCC dam, scientific and technical research, design, construction technique, operation experience, dam construction technology
  • 相关文献

参考文献10

  • 1国际碾压混凝土学术讨论会论文集,1999年
  • 2马福恒,大坝安全监测,1999年,1期
  • 3水力发电,1998年,9期
  • 4水利水电技术,1998年,7期
  • 5水利水电技术,1998年,9期
  • 61996碾压混凝土筑坝技术交流会论文集,1996年
  • 7沈崇刚,水力发电,1996年,9/10期
  • 8国际碾压混凝土学术讨论会论文集,1995年
  • 9国际碾压混凝土坝学术讨论会论文集,1991年
  • 10沈崇刚,水力发电与坝工建设,,1991年,11期