700t客专预制箱梁张拉施工控制技术综述 被引量:2

A survey on the control technology of stretch-drawing prefabrication of box girders for 700-t passenger special line summary
下载PDF
导出
摘要 结合成绵乐客运专线700 t预制箱梁预应力的张拉控制过程,根据钢绞线的物理和力学性能指标及预应力施工工艺流程,详细阐述700 t箱梁的张拉施工工艺和施工技术要求以及控制要点,对客专700 t预制箱梁张拉施工控制技术进行系统的总结。 On the basis of the stretch-drawing control construction of the 700-t box girders for Chendu-Mianyang-Leshan Passenger Dedicated Railway,the physical and mechanical performance indicators of steel stranded wires,and the construction technology process for prestressing reinforcement,this paper expatiates on the stretch-drawing construction technology for 700-t box girders,the specification requirements of construction techniques and control points.Furthermore,we systematically summarize the control technology of stretch-drawing prefabrication of box girders for 700-t passenger special line.
作者 杜文举
出处 《石家庄铁路职业技术学院学报》 2011年第1期59-63,共5页 Journal of Shijiazhuang Institute of Railway Technology
关键词 预制箱梁 钢绞线 张拉 Precasting box girders Steel stranded wires Stretch-drawing
  • 相关文献

参考文献4

  • 1铁路桥涵施工规范[S].(TB10203-2002).
  • 2客运专线铁路桥涵工程施工质量验收暂行标准[S].铁建设[2005]160.
  • 3号铁路混凝土工程施工质量验收补充标准[S].铁建设[2005]160号.
  • 4铁路桥涵钢筋混凝士和预应力混凝土结构设计规范[S].(TBl0002.3-2005).

同被引文献6

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部