摘要
利用立井凿井设施施工井底煤仓,根据立井设施的布置情况设计煤仓的辅助运输系统,在煤仓施工中提出了慢速绞车提升、短段掘砌作业的施工工艺,根据施工特点针对性的制定了劳动作业组织及安全管理措施。
This construction item to drill a well the facility construction bottom of the well coal bin using the vertical shaft,has designed the coal bin xiliary haulage system according to the vertical shaft facility's arrangement situation,and proposed in the coal bin construction the slow winch promotion,short Duan Jue build the work the construction craft,and according to construction characteristic pointed formulation work organization and safety control measure.
出处
《山东煤炭科技》
2011年第1期19-20,共2页
Shandong Coal Science and Technology
关键词
立井
凿井设施
施工
煤仓
The vertical shaft Drills a well the facility Construction
Coal bin