针对铜矿峪矿530 m中段有轨运输设计,对所提出的6 m3底卸式矿车运输方案进行了分析和计算,从而为确定方案提供正确的依据。
According to the transportation design pattern of 530 m middle section in Tongkuangyu mine,the transportation pattern of 6 m3 bottom-dump tramcar is analyzed and calculated in this paper,in order to provide correct references for the determination of project.
出处
《有色金属(矿山部分)》
2011年第2期47-48,54,共3页
NONFERROUS METALS(Mining Section)
关键词
有轨运输
牵引能力
电机车
底卸式矿车
track transportation
tractive capability
electric locomotive
bottom-dump tramcar