摘要 针对求解资源受限项目调度问题(RCPSP),提出了基于差分进化(DE)的混合粒子群算法(PSODE)。通过在PSO种群和DE种群之间建立一种信息交流机制,使信息能够在两个种群中传递,以避免个体因错误的信息判断而陷入局部最优点。采用标准测试函数和具体算例进行检验,结果表明PSODE算法可以较好地解决RCPS问题。 For resource-constrained project scheduling problem(RCPSP),proposed the hybrid particle swarm optimization(PSODE)based on differential evolution(DE).The new algorithm established an information exchange mechanism between the PSO population and DE population,transferred the allowing information in two population to avoid the individual to reach a local optimum for wrong information determine.This paper tested the effectiveness of the algorithm by using the test function and specific examples.The results show that PSODE algorithm can well solve RCPSP.
出处 《计算机应用研究》 CSCD 北大核心 2011年第4期1286-1289,共4页 Application Research of Computers
基金 重庆市科委自然科学基金计划资助项目(CSTC 2008BB2173) 中央高校基本科研业务费资助项目(CDJXS11110014)
关键词 差分进化混合粒子群算法 粒子群算法 差分进化算法 项目调度 hybrid particle swarm optimization algorithm based on differential evolution particle swarm optimization(PSO) differential evolution project scheduling
  • 相关文献

参考文献10

  • 1KOLISCH R, HARTMANN S. Experimental investigation of heuristics for resource-constrained project scheduling: an update[ J]. European Journal of Operational Research,2006,174( 1 ) :23-37.
  • 2杜焱,彭武良.一种求解资源受限项目调度问题的遗传算法[J].沈阳理工大学学报,2009,28(1):70-73. 被引量:2
  • 3郑超,高连生.蚁群算法在资源受限项目调度问题中的应用[J].计算机工程与应用,2005,41(27):205-208. 被引量:16
  • 4喻小光,战德臣,聂兰顺.应用遗传模拟退火算法实现资源受限项目调度[J].计算机工程与应用,2009,45(24):17-20. 被引量:10
  • 5王巍,赵国杰.粒子群优化在资源受限工程调度问题中的应用[J].哈尔滨工业大学学报,2007,39(4):669-672. 被引量:11
  • 6PRICE K. An introduction to differential evolution[ M]. New Ideas in Optimization. Maidenhead : McGraw-Hill, 1999:79-108.
  • 7KENNEDY J, EBERHART R. Particle swarm optimization [ C ]// Proc of IEEE International Conference on Neural Networks. 1995: 1942-1948.
  • 8SHI Y, EBERHART R C, EMPIRICAL C. Experimental study of particle swarm optimization [ C ]//Proc of the World Multiconference on Systemics Cybernetics and lnfommtics. 2000 : 1945-1950.
  • 9KELLY J E Jr. The critical path method: resource planning and scheduling[M]//MUSH J F, THOMPSON G L. Industrial Scheduling. Englewood Cliffs : Prentice-Hall, 1963.
  • 10KOLISCH R. Serial and paralled resource-constrained project schedu- ling methods revisited: theory and computation [J]. European dournal of Operational Research, 1996,90 ( 2 ) :320- 333.

二级参考文献43

  • 1Brucker P, Drexl A, Mohring R,et al. pro- ject scheduling: notation, classification, models, and methods [ J]. European Journal of Operational Research, 1999,112( 1 ) : 3-41.
  • 2Rainer Kolisch, Sonke Hartmann. Experimental investigation of heuristics for resource-constrained project scheduling: An Update [ J]. European Journal of Operational Research, 2006,174( 1 ) : 23 -37.
  • 3Kolisch R. Serial and parallel resource-constrainedproject scheduling methods revisited : theory and computation [ J ]. European Journal of Operational Research, 1996, 90(2) : 320-333.
  • 4Kolisch R, Sprecher A. PSPLIB-A project scheduling problem library[ J]. European Journal of the operational search, 1997, 96 ( 1 ) : 205-216.
  • 5Alcaraz J, Maroto C. A robust genetic algorithm for resource allocation in project scheduling [ J ]. Annals of Operation Research, 2001, 102(1) : 83-109.
  • 6Hindi K S, Yang H, Fleszar K. An evolutionary algorithm for resource-constrained project scheduling[J]. IEEE Transactions on Evolutionary Computation, 2002, 6(5) : 512-518.
  • 7Bouleimen K, Lecocq H. A new efficient simulated annealing algofithm for the resource-constrained project scheduling problem and its multiple mode version [ J ]. European Journal of Operational Research, 2003, 149(2) :268-281.
  • 8Schirmer A. Case-based reasoning and improved adaptive search for project scheduling[ J]. Naval Research Logistics, 2000, 47 (3) : 201-222.
  • 9Brucker P, Knust S, Schoo A, et al. A branch and bound algo- rithm for the resource constrained project scheduling problem [ J ]. European Journal of Operational Research, 1998, 107 (2) : 272-288.
  • 10Hartmann S. A competitive genetic algorithm for resource-constrained project scheduling[ J]. Naval Research Logistics, 1995, 45 (7) :733-750.

共引文献28

同被引文献99

引证文献8

二级引证文献37

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部