介绍了二期镁白灰生产工程的工艺方案及建设投入。在生产过程中对冶金镁白灰的破碎工艺进行了优化。从建设投入及运行效果等方面阐述了新方案的工艺合理性及先进性。
The process plan and construction investment for the phase Ⅱ magnesia lime production project are described.During production process,the crushing process for metallurgical magnesia lime is optimized.The rationality and advanced feature of the process of the new plan are expounded from the aspects of construction investment,operation result and so on.
出处
《耐火与石灰》
2011年第2期15-17,共3页
Refractories & Lime
关键词
一期工程
二期工程
镁白灰
破碎
优化
Phase Ⅰ project
Phase Ⅱ project
Magnesia lime
Crushing