摘要
对天生桥一级水电站工程的拦河大坝-混凝土面板堆石坝的主要施工方法进行了介绍,同时对施工中遇到的一些实际问题进行探讨,阐述了我们的实际作法,并结合施工实际提出了建议。
The construction method of rock fill dam with concrete facing for the 1st step of Tianshengqiao Hydropower station is expounded in detail, and the problems met in construction are discussed. While, the way to deal with these problems are shown, some suggestions are put forward according the construction practice.
出处
《陕西水力发电》
1999年第2期33-37,共5页
Journal of Shaanxi Water Power
关键词
施工
混凝土
面板堆石坝
水电站
经验
Engineering construction
practical problems
experience
rock fill dam with concrete facing