讨论了水电站机组的投运状况,建立了考虑机组空载状况和具有强制性开机约束的厂内经济运行模型.针对模型含有0-1 变量的特点,应用动态规划方法求解.实例研究表明,模型合理,算法可行、有效.
Unit Commitment(UC) at hydropower plants is discussed. The economical operation models considering the state of no load and compulsory contraints for unit start are built. According to the characteristics of these models containing 0 1 variables, dynamic programming method is used to solve the problems. Case study shows that the models are reasonable and the method is efficient and feasible.
出处
《水电能源科学》
1999年第3期27-30,共4页
Water Resources and Power
关键词
水电站
经济运行
优化模型
动态规划方法
economical operation
optimization model
dynamic programming method
hydropower plant