错综复杂的地下管线的处理往往制约了工程进展,同时工程施工也对管线有所影响,大大增加了施工费用和风险。在施工过程中应将管线梳理清楚,并结合工程筹划制定出切实可行的管线处理方案,以保证工程施工的顺利进行。结合西江引水工程的建设实践经验,对施工中涉及的地下管线的迁改及保护进行初步探讨。
The project progress is often constrained by the complicated underground pipe network, and the project construction has a negative effect on the pipeline, increasing the construction cost and risk. Therefore, a feasible plan should be determined by a systematic survey of the pipe network, combined with the whole project scenario, to ensure the success of the project. Based on the experience of Xijiang River water diversion project, a preliminary discussion on the movement and protection of existing underground pipeline in the project is made.
出处
《中国给水排水》
CAS
CSCD
北大核心
2011年第8期6-9,共4页
China Water & Wastewater
基金
国家水体污染控制与治理科技重大专项(2009ZX07423-004)
关键词
西江引水工程
地下管线
迁改
保护
Xijiang River water diversion project
underground pipeline
movement
protection