摘要
为了优化施工进度计划,简单介绍了关键链技术及其计划方法,分析关键链技术在工程领域的局限性,改善安全时间的计算、缓冲区的设置和缓冲时间计算的方法;建立施工计划与排程模型,实现施工计划与排程的应用。
In order to optimize the construction schedule,briefly reviews the Critical Chain method and its programs,analyzes the limitations in the area of construction management in our country,improves some methods about the safety time calculation,the buffer setting and buffer time calculation.A model of construction planning and scheduling is established,which is helpful for advance performance of project management.
出处
《建筑经济》
2011年第4期40-43,共4页
Construction Economy
关键词
关键链技术
工程管理
计划与排程
模型
应用
Critical Chain method
construction management
planning and scheduling
model
application