摘要
建国初期,我国在经济技术水平十分薄弱的基础上开始了地下水电站建设。1980年后,引进了先进技术,设计理论突破,施工技术更新,又好又快地建成了一批高水平的地下水电站,积累了丰富的经验,地下水电站建设取得了巨大的成就。实践表明,地下水电站具有多方面的优越性,有着广阔的发展前景。
In the early years of new China, the construction of underground hydropower stations is begin even if the economy and technology is very weak at that time. Since 1980, a number of underground hydropower stations in China were soundly and fast built, rich experiences were accumulated and great achievements were made with the introduction of advanced technology, the breakthrough of design theory and the update of construction technology. Practices show that the underground hydropower stations have many advantages, and have broad prospects for development.
出处
《水力发电》
北大核心
2011年第3期18-20,27,共4页
Water Power
关键词
地下水电站
设计理论
施工技术
围岩稳定性
underground hydropower station
design theory
construction technology
surrounding rock stability