摘要 为研究预制混凝土结构的钢筋连接方法,设计制作了81个预制混凝土插入式预留孔灌浆钢筋锚固拉拔试件,考虑钢筋直径、混凝土强度、锚固长度等主要影响参数.连续加荷拉拔试验结果表明:灌浆锚固试件的最终破坏状态都是外部钢筋屈服或被拉断,没有发生异常锚固破坏,而且在基本锚固长度基础上分别减小为0.9、0.8倍时还有较大安全储备.根据试验数据结果给出插入式预留孔灌浆钢筋的基本锚固长度为0.8 l a. To study the connection method between reinforced bars of the precast concrete (PC) structure, 81 plug -in filling hole for lap -joint of steel bar sample tests were made, and the main factors, such as reinforced bar diameter, concrete strength and anchorage length etc. were considered during the tests. The test results indicated that the ultimate failure state of all the anchoring specimens were the external reinforced bar yielding or broken up by pulling, and the abnormal anchorage was not destroyed. When the basic anchoring length was reduced by 10% or even 20%, specimens still showed enough safety. Based on this, the basic anchoring length of plug - in filling hole for lap - joint of steel bar can be given as 0. 8 l a.
出处 《哈尔滨工业大学学报》 EI CAS CSCD 北大核心 2011年第4期28-31,36,共5页 Journal of Harbin Institute of Technology
关键词 住宅产业化 预制混凝土结构 装配式结构 钢筋锚固搭接 粘结滑移 housing industrialization precast concrete structure assembly structure reinforcement anchorage & lapping bond -slip behavior
  • 相关文献

参考文献9

  • 1徐有邻.钢筋与混凝土粘结锚固的分析研究[J].建筑科学,1992,8(4):18-24. 被引量:23
  • 2王国杰,郑建岚.自密实混凝土与钢筋的粘结锚固性能试验研究[J].福州大学学报(自然科学版),2004,32(3):334-338. 被引量:12
  • 3赵高荣,魏仲文,李改敏.混凝土结构中受拉钢筋的锚固作用[J].西山科技,2000(5):11-12. 被引量:1
  • 4YERLICI V A, TURAN O. Factors affecting anchorage bond strength in high -performance concrete [ J]. ACI Structural Journal, 2000,97 (3) :499 - 507.
  • 5ENRICO S, SUCHART L. Responses of reinforced concrete members including bond - slip effects[J].ACI Structural Journal, 2000, 97 (6) : 831 - 839.
  • 6ALMEIDA de F, MENEZES F,DEBS E, et al. Bond - slip behavior of self - compacting concrete and vi- brated concrete using pull - out and beam tests [ J ]. Materials and Structures/Materiaux et Constructions, 2008, 41 (6) : 1073 - 1089.
  • 7WILSON J L, ROBINSON A J, BALENDRA T. Performance of precast concrete load - bearing panel structures in regions of low to moderate seismicity [ J]. Engineering Structures, 2008,30 (7) : 1831 - 1842.
  • 8KURAMA Y C. Precast/prestressed concrete structures under natural and human - made hazards: special issue [ J ]. Journal of Structural Engineering, 2007,133 ( 11 ) : 1487 - 1488.
  • 9MORGEN B G, KURAMA Y C. Seismic design of friction- damped prccast concrete frame structures [J]. Journal of Structural Engineering, 2007, 133 (11):1501 -1511.

二级参考文献4

  • 1郑建岚.现代混凝土结构技术[M].北京:人民交通出版社,2000..
  • 2高向玲 李杰.高性能混凝土与钢筋的粘结性能[A].中国土木工程学会高强与高性能混凝土委员会.高强与高性能混凝土及其应用[C].长沙,2001.523-531.
  • 3徐有邻,邵卓民,沈文都.钢筋与混凝土的粘结锚固强度[J]建筑科学,1988(04).
  • 4过镇海,张秀琴,张达成,王如琦.混凝土应力-应变全曲线的试验研究[J]建筑结构学报,1982(01).