龙滩碾压混凝土夏季(高气温)施工措施研究——高温缓凝减水剂

Research on Construction Measurement of RCC Grouted in High temperature Summer for Longtan Project by Developing High temperature Set retarding and Water reducing Admixture
下载PDF
导出
摘要 通过室内外和现场论证性试验,对碾压混凝土初凝时间进行测定,证实研制得出的高温缓凝减水剂,在夏季高气温条件下,碾压混凝土初凝时间达到6h~8h的要求。通过对掺高温缓凝减水剂碾压混凝土的物理力学特性和耐久性能的研究,最终推荐出BZ高温缓凝减水剂。文中研究了水泥和细骨料的不同对碾压混凝土初凝时间的影响;研究了环境条件对碾压混凝土初凝时间的影响,同时给出近似关系式。 By measuring the initial setting time of RCC indoor,outdoor and in situ,it was proved that the initial setting time of RCC reached 6~8 hours in high temperature summer by adopting the developed high temperature set retarding and water reducing admixture.The research was carried out on the physical mechanical characteristics and durability of RCC which was admixed with high temperature set retarding and water reducing admixture,as a result the admixture named BZ was recommended.In this paper the influence of cement type,fine aggregate type and environmental conditions on the initial setting time of RCC was studied,and the approximate relational expression was given.
作者 林长农
出处 《红水河》 1999年第2期19-23,30,共6页 Hongshui River
基金 "八五"国家科技攻关项目
关键词 高温缓凝水剂 碾压混凝土 大坝 夏季 施工措施 high temperature set retarding and water reducing admixture, RCC, initial setting time, high air temperature
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部