摘要
在大型水利水电施工中,经常遇到岩质高边坡稳定问题,天荒坪抽水蓄能电站500kV开关站所处的地形地质条件非常复杂,本文着重介绍在边坡开挖和支护过程中,根据不同的地形地质情况所采取的控制爆破和支护措施。
It is very often to encounter the high rock slope stability problem in construction of a water conservancy project or a hydropower project. The 500 kV substation of the Tianhuangping pumped-storage hydropower station is located in a topographically and geologically complicated area. This paper deals with the controlled blasting and supporting measures taken in the light of the different topographical and geological conditions during the slope excavation and supporting.
出处
《云南水力发电》
1999年第2期30-33,共4页
Yunnan Water Power