摘要
某水电站压力管道基础开挖与填筑已全部完成,镇墩也正在施工之中,但是洪水过后,对压力管道部分产生了很大程度的损坏,本文针对损坏现场,进行了相应有效的施工修复方案设计,进一步介绍了相应的施工方法。
The basis of a hydropower foundation excavation and filling has been completed, the bedding is also under construction,but after the flood,some of the pressure pipe produced a large degree of damage,for the damaged on the site ,this paper introduces the appropriate construction method according to the corresponding effective construction repair program design.
出处
《吉林水利》
2011年第4期15-17,共3页
Jilin Water Resources
关键词
洪水
压力管道
修复
施工方法
flood
pressure pipeline
repair
construction method