摘要
某工程地基处理采用冲击成孔灌注桩,通过试桩的施工及检测情况说明该种桩的施工难点在于处理塌孔,针对试桩施工出现的问题对工程桩施工采取措施,达到正确应用冲击成孔灌注桩的目的。
Cast in situ bored pile is adopred for the ground treatment in a project.By the construction and detect of the test pile,it is proved that the difficulty in the construction of the pile is to deal with collapse and take conesponding measures.
出处
《太原理工大学学报》
CAS
1999年第5期542-545,共4页
Journal of Taiyuan University of Technology
关键词
地基处理
冲击成孔
施工
灌注柱
ground treatment
punching boring
construction problem