摘要
结合白水峪水电站现场实际情况,分析了电站改造前调速器存在的问题和相应的解决办法。针对调速器改造的实践经验,介绍了DFWT-100-4.0可编程调速器的相关情况。
In connection with the practical conditions on site of Baishuiyu Power Plant,the problems of the governor before the reform and the corresponding measures to solve them were analyzed.According to the practical experience in governor innovation,this paper described the relevant conditions of DFWT-100-4.0 programmed governor.
出处
《水电与新能源》
2011年第3期55-57,共3页
Hydropower and New Energy
关键词
白水峪水电站
调速器
技术改造
Baishuiyu Hydropower Plant
governor
technical innovation