摘要 某大型水电站位于雅砻江中游,在调查期间发现短短30 km河段内发育10个特大型-巨型古滑坡体,滑坡体规模巨大,方量4 000×104~12 000×104m3不等,沿江长度达数千米,最大深度达200 m以上,且70%发育于河流右岸,滑坡群对拟建的工程影响巨大且不可回避。通过因素分析获知:滑坡群在此处的发育有其必然性,其与河谷形态、陡峻的深切峡谷地貌、软硬相间的岩层结构、分区性前波大断裂的切割等因素密切相关,其形成机制可归纳为滑移-拉裂型、滑移-弯曲型(溃屈)、弯曲-拉裂型(倾倒)3大类。最后结合滑坡的稳定性和拟选坝址位置对工程影响进行评价,得出如下结论:工程区滑坡数量众多,与坝址相间分布,在上、中、下坝址间选择上坝址对工程安全性最为有利,尤其是避开了下游有复活迹象的3个特大型滑坡,最后提出相应工程建议,可对工程建设起一定参考。 The investigated large hydropower station is located in the middle reach of Yalong River.During the investigation,it is found that there are 10 extra-large and huge ancient landslides developed in a short river section of 30 km.Survey shows that the landslide group has enormous and unavoidable impact on the proposed project with huge landslide volume of 4 000×104 m3 to 12 000 ×104 m3 and a total length of several kilometers along the river,as well as a maximum depth of over 200 m,and 70% of the landslide developing at the right bank.In this paper,factor analysis shows that the development of landslide group is inevitable as it is closely related to factors such as the valley shape,steep canyon geomorphology,alternatively distributed soft and hard rock layers,and the cutting of partitioned reverse fracture.The formation mechanism can be concluded into 3 categories,namely sliding-tension fracturing,sliding-bending(buckling),and bending-tension fracture(collapse).Finally,based on the assessment of landslide stability and the influence of dam location on the project,the following conclusion is obtained: as the landslides and dam sites are interspersed,the upstream dam site is the best choice for engineering safety as it can avoid three huge landslides which have signs of reactivation.Corresponding project proposal is also put forward.
出处 《长江科学院院报》 CSCD 北大核心 2011年第5期9-13,共5页 Journal of Changjiang River Scientific Research Institute
关键词 滑坡群 形成条件 工程影响 landslide group formation condition project influence
  • 相关文献

参考文献5

二级参考文献12

  • 1钱家欢 殷宗泽.土工原理及计算[M].北京:中国水利水电出版社,1996.326-327.
  • 2中国科学院武汉岩土力学研究所.武纲大冶铁矿狮子山北帮A区尖F9断层上盘V-24m水平以上不稳定区边坡治理与监测研究总报告[M].,1992..
  • 3[2]Wang Yunsheng,He Jie,Hu Xiao Qiang.Landslide Reactivation Caused by the Road Construction in Sichuan,China;Engineering Geology for Developing Countries -Proceedings of 9th Congress of the International Association for Engineering Geology and the Environment.Durban,South Africa,2002,16-20 September 2002 -J.L.van Rooy and C.A.Jermy,editors.
  • 4钱家欢,土工原理与计算(第2版),1996年,326页
  • 5中国科学院武汉岩土力学研究所,武钢大冶铁矿狮子山北帮A区尖F9断层上盘V-24m水平以上不稳定区边坡治理与监测研究总报告,1992年
  • 6建筑地基基础设计规范GBJ7-89,1989年
  • 7《工程地质手册》编写委员会.工程地质手册[M].北京:中国建筑工业出版社,1992..
  • 8地质矿产部成都水文地质工程地质中心 成都地质学院 水利部长江水利委员会勘测总队.长江三峡工程库岸稳定研究[M].北京:中国科学技术出版社,1992..
  • 9朱大勇.边坡临界滑动场及其数值模拟[J].岩土工程学报,1997,19(1):63-69. 被引量:97
  • 10朱大勇,钱七虎,周早生,郑鸿泰.岩体边坡临界滑动场计算方法及其在露天矿边坡设计中的应用[J].岩石力学与工程学报,1999,18(5):567-572. 被引量:31