摘要
Taum Sauk上水库重建工程主要是新建一座现代化的混凝土面对称碾压混凝土(RCC)坝来取代原有的土石坝。由于该坝是美国最大的RCC项目并采用了对称断面和相对低强度的RCC,设计中需要解决许多问题。文章总结了相关设计事项,并简要介绍了施工过程,供参考。
The Taum Sauk upper reservoir rebuild project primarily consisted of the reconstruction of the existing inoperable rock fill upper reservoir with the construction of a modern concrete faced symmetrical roller compacted concrete(RCC) dam.As the project is the largest RCC project constructed in the USA and it has asymmetrical cross-section with relatively low strength RCC,numerous design issues arose during the design process.This paper summarized these issues and introduced its construction,for reference.
出处
《大坝与安全》
2011年第1期67-74,共8页
Dam & Safety