根据巢湖市裕溪路东桥土石围堰施工中,采用水泥搅拌桩连续墙加固围堰坡脚,结合实际施工,介绍这一施工方法。
According to the construction of the Earth-rock cofferdam in east bridge,Yuxi Road,Chaohu City,the which uses the deep mixing pile diaphragm wall to reinforce the slope of the cofferdam,combining with the practical construction,introduces this construction method.
出处
《价值工程》
2011年第16期81-81,共1页
Value Engineering
关键词
土石围堰
水泥搅拌桩连续墙
加固
the Earth-rock cofferdam
the deep mixing pile diaphragm wall
reinforcement