摘要 介绍津秦客专宁车沽永定新河特大桥深水基础钢板桩围堰的设计与施工。根据该桥实际情况,通过多种工况的受力分析与计算,从施工安全、成本、工期等多方面进行比较,得出合理的结构方案,并对关键施工工艺作具体叙述。 This paper introduces the design and construction of steel sheet pile cofferdam for deep water foundation in Ningchegu Yongdingxin River Bridge in the Tianjin-Qinhuangdao Railway Passenger Line.According to the actual situation of the bridge,through a variety of stress analysis and calculation of working conditions,this paper offers a reasonable structure program by comparison of construction safety,cost,construction period and so on,and describes the key construction technology.
作者 郭建东
出处 《石家庄铁路职业技术学院学报》 2011年第2期33-36,共4页 Journal of Shijiazhuang Institute of Railway Technology
关键词 深水基础 钢板桩围堰 设计 施工 deep water foundation steel sheet pile cofferdam design construction
  • 相关文献

参考文献4

  • 1TB 10002.5-2005,铁路桥涵地基和基础设计规范[S].
  • 2GB50017-2003.钢结构设计规范[S].[S].,..
  • 3简明施工计算手册[M].(第三版)(汪正荣主编)中国建筑工业出版社,2005.7.
  • 4GB50007-2002.建筑地基基础设计规范[S].[S].,..

共引文献3933

同被引文献10

引证文献2

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部