摘要
甬台温铁路邵家隧道,在施工至离洞口134m处发生了塌方。在确保施工安全的前提下,采用了小导管注浆加固和七步台阶法开挖的方式对塌体进行了处理,并安全顺利的通过了塌方段。
Shaojia tunnel of Yongtaiwen railway took place collapse in the construction from the hole 134m.In the premise of ensuring safe construction,it used small tube grouting and seven-step bench excavation method to deal with the collapse body and passed the safe cave section smoothly.
出处
《价值工程》
2011年第17期83-84,共2页
Value Engineering
关键词
塌方
小导管
七步台阶开挖法
landslides
small pipe
seven-step bench excavation method