以温州珊溪水利枢纽珊溪电厂为例,介绍了高压限流熔断器组合保护装置在电厂运行中存在的问题,对其改造方案进行了分析,阐述了系统采用FURV的优越性以及FURV的参数设计与结构。
Taking Shanxi Power Plant of Shanxi Water Control Project in Wenzhou City as an example,this paper introduces some problems existing in the application of combined protective device of high-voltage current-limiting fuse in the operation of the power plant,analyzes its transformation scheme,and expounds the advantages of FURV and the parameter design and structure of FURV.
出处
《科技情报开发与经济》
2011年第13期218-219,228,共3页
Sci-Tech Information Development & Economy
关键词
高压限流熔断器
组合保护装置
改造方案
FURV
珊溪电厂
high-voltage current-limiting fuse
combined protective device
transformation scheme
FURV