挖掘机生产能力计算方法的研究 被引量:2

Study on methods of calculating excavator productivity
原文传递
导出
摘要 挖掘机的生产能力既是挖掘机的一项主要的技术指标,也是一项综合指标,而工作循环时间又是确定挖掘机生产能力的关键因素。在综合分析影响生产能力因素的基础上,结合WK系列挖掘机,首次提出了工作循环、挖掘时间和回转时间的经验计算公式,为最终确定和提高挖掘机的生产能力奠定了基础。 The productivity is not only one of main technical indexes but a complex index, and the working cycle time is the main factor to determine the loader productivity. Based on analysing the factors affecting the productivity, experiential calculation methods for working cycle time, excavating time and turning time are proposed with WK series excavators being taken for example, which offers references for finally determining and enhancing the loader productivity.
出处 《矿山机械》 北大核心 2011年第6期40-43,共4页 Mining & Processing Equipment
关键词 挖掘机 生产率 工作循环时间 挖掘时间 回转时间 excavator productivity working cycle time excavating time turning time
  • 相关文献

参考文献10

  • 1В.В.Ржевский.Процессы Омкрмый Горныхработ[M].Москва:НЕДРА,1978.
  • 2林贵瑜,李爱峰,李奎贤.确定挖掘阻力关键因素值与方法的研究[J].东北大学学报(自然科学版),2010,31(12):1761-1764. 被引量:9
  • 3美国P&H公司.美国P&H产品样本:P&H 4100A,P&H 4100B[Z]:2.
  • 4太原重工股份有限公司.WK系列挖掘机产品样本[X],1964:3.
  • 5太原重工股份有限公司.WK系列挖掘机产品样本[X],2004:3.
  • 6太原重工股份有限公司.WK系列挖掘机产品样本[X],1986:3.
  • 7太原重工股份有限公司.WK系列挖掘机产品样本[X],2002:3.
  • 8太原重工股份有限公司.WK系列挖掘机产品样本[X],2003:3.
  • 9太原重工股份有限公司.WK系列挖掘机产品样本[X],2005:3.
  • 10太原重工股份有限公司.WK系列挖掘机产品样本[X],2008:3.

二级参考文献9

  • 1Волйов Д П. Динвмические Нагрузки в Универсальных Экскаваторах-Кранах[K]. Москва: Государственное научно-Техническое Издательство Машиностроительной Литературы,1958:13-35,113-127.
  • 2阎书文.机械式挖掘机设计[M].北京:机械工业出版社,1983:12-24.
  • 3Ананин В Г. Исследование усилий в злементах рабочего обрудования карьерных экскаваторов с механическим приводом[Ж]. Механизачия Строимельства,2008(2):13-15.
  • 4Karev G A. Approximate determination of an optimal width of excavation in power shovel operation[J]. Power Technology and Engineering ( formerly Hydrotechnical Construction ), 1974,8(11) : 1034 - 1038.
  • 5Rodionov G V, Sytnik V F. Determining the resistive force exerted by the rock against the shovel of a loading machine [R]. Kiev: State Research and Planning Institute for the Coal Industry, 1968 : 128 - 134.
  • 6Vylomov V P, Kovalev M N. Using hydraulic excavators for selective mining of magnesite[J]. Refractories and Industrial Ceramics, 1982,23 : 414 - 417.
  • 7Li Y, Frimpong S. Hybrid virtual prototype for analyzing cable shovel component stress[J ]. The International Journal of Advanced Manufacturing Technology, 2008, 37 : 423 - 430.
  • 8Roy S K, Bhattacharyya M M. Maintainability and reliability analysis of a fleet of shovels[J]. Min Technol, 2001,110(3) : 163 - 179.
  • 9李奎贤,王新中,邹宜民.合理挖掘轨迹的确定及意义[J].矿山机械,2000,28(8):14-15. 被引量:11

共引文献8

同被引文献4

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部