金沙江下游河段规划中的乌东德、白鹤滩电站经过工程预可研和可研论证,具备装设单机容量1 000MW机组的条件。对1000MW水轮发电机组设计制造及工程应用技术可行性研究新进展进行了总结,并指出了下阶段研究的重点。研究结果表明:立足国内技术,乌东德、白鹤滩1000MW水轮发电机组的设计、制造、运输是可行的,不存在大的制约因素。
The planned hydro-power projects of Wudongde and Baihetan in the lower reach of Jinshajiang River are to be built soon after the pre-feasibility and feasibility study,where the single-machine capacity can reach to 1 000 MW.The new development for the feasibility research on design,manufacture and engineering application technology are summarized for 1 000 MW hydro-generator units,and the research emphases for the next stage presented.Based on the domestic technology,the studies show that it is feasible to design,manufacture and transport of 1 000 MW hydro-generator units in Wudongde and Baihetan,without big constraints existing.
出处
《电力建设》
2011年第6期62-66,共5页
Electric Power Construction