过河管基槽开挖及基础处理的技术要点 被引量:2

Technical Key Points of Cross River Pipeline Trench Excavation and Foundation Treatment
原文传递
导出
摘要 广州市西江引水工程已通水投运,管线总长为71.6 km。北江过河管道沉放安装作为其中的主要节点,在参建各方的精心组织与部署下顺利完成。以该大型管道安装为例,分析了沉管施工的要点问题,介绍了管道基槽开挖及基础处理措施。 The Guangzhou Xijiang River Water Diversion Project, including 71.6 km pipeline, has been put into operation. Under the elaborate organization and arrangement from all participators, the Northern River cross river pipeline construction, as the main part of the whole project, has been accom- plished perfectly. Taking the large-scale pipeline installation for example, some key points of sinking pipeline method are analyzed, and the foundation ditch excavating and foundation treatment are introduced.
作者 李志坚
出处 《中国给水排水》 CAS CSCD 北大核心 2011年第12期1-4,共4页 China Water & Wastewater
基金 国家水体污染控制与治理科技重大专项(2009ZX07423-004)
关键词 过河管道 大口径钢管 基槽 基础处理 cross river pipeline treatment large diameter steel pipe foundation ditch foundation
  • 相关文献

参考文献2

二级参考文献8

共引文献54

同被引文献9

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部