摘要 特高拱坝与一般高拱坝相比,其结构性态更加复杂,因此,其变形安全预报控制值必须进行专门的研究。文中探讨了特高拱坝的定义与特点,分析了特高拱坝的变形特性,提出了特高拱坝一级变形预报控制值建立的准则与方法。工程案例表明,该方法切实可行。 Compared with the conventional high arch dam, the structural behavior of super-high arch dam is more complicated, and then, special study must be made on its deformation safety prediction control value. The definition and characteristics of the super-high arch dam are discussed herein, furthermore, the deformation behavior of the dam is analyzed as well; from which the criteria and method of establishing the primary deformation prediction control value for the dam are put forward. The relevant actual engineering case shows that this method is feasible in the practice.
作者 陈锋 谷艳昌
出处 《水利水电技术》 CSCD 北大核心 2011年第6期22-25,共4页 Water Resources and Hydropower Engineering
基金 江苏省自然科学基金项目(BK2010125) "十一五"国家科技支撑计划课题(2009BAK56B04)
关键词 特高拱坝 一级变形 预报控制值 大坝安全监测 super-high arch dam primary deformation, prediction control value dam safety monitoring
  • 相关文献

参考文献4

二级参考文献2

  • 1国家地震局.中国地震烈度区划图[M].北京:地震出版社,1990..
  • 2GB50011.2001.建筑抗震设计规范 [S].[S].北京:中国建筑工业出版社,2001..

共引文献34

同被引文献9

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部