摘要
汶川地震断裂带科学钻探Ⅱ号孔(WFSD-2)由于设计变更,需要在311 m以上孔段下入活动套管并在其环隙灌注充填液。通过模拟实验,主要对3种充填液的黏滞特性进行了研究,计算确定了其相应状态下的黏滞系数,最终确定以2%浓度的水解聚丙烯酰胺(PHP)溶液作为活动套管环隙填充液。
As the design of Hole Ⅱ of the Wenchuan earthquake fault scientific drilling project changes,it is required to down an active casing into the hole from 0 to 311 meters and to fill some fluids into the annulus.Through simulation experiments,the viscious properties of three filling fluids are studied,and their viscosities under the corresponding state is calculated and determined.Finally,the concentration of 2% hydrolytic polyacrylamide(PHP) solution it determined as the filling fluid in the active casing annulus.
出处
《成都理工大学学报(自然科学版)》
CAS
CSCD
北大核心
2011年第3期339-343,共5页
Journal of Chengdu University of Technology: Science & Technology Edition
基金
科技部科技支撑计划专项
关键词
科学钻探
活动套管
充填液
scientific drilling
active casing
filling fluid