摘要
将筒仓工程库壁滑升模板体系和库壁滑升模板构造及直形挡墙模板系统进行一体化施工的统筹设计,在库底板以下部位,采用库壁与直形挡墙同步施工的滑动模板构造体系,库底板以上部位采用适合单仓施工的库壁滑动模板技术体系,在模板构造方面,实现两种模板构造的兼容和相互转换,配合合理的施工工艺和作业方法,完成超大直径钢筋混凝土筒仓库壁和仓体结构有拖带或无拖带施工。
Silo engineering library wall slippery rise template system and library wall slippery rise template structures and retaining straight form integrated construction of template system in library, overall design, the library floor following parts with straight retaining wall of sliding si- multaneous construction of fractal structure system,the library floor template for more parts adopt single warehouse construction library wall formwork technology system, in slide template teetonically, realize template tectonic compatible and mutual conversion, cooperate with the rea- sonable technology of construction and operation method,complete cylinder warehouse wall and warehouse body structure have towage or no towage construction.
出处
《混凝土》
CAS
CSCD
北大核心
2011年第6期159-161,164,共4页
Concrete
关键词
一体化施工
统筹设计
相互转换
integration construction
overall design
mutual conversion