淤泥质地层盾构始发洞门地层改良技术 被引量:3

Silty Stratum Reinforcement Technique Applied for Starting Hole of Shield Tunneling
下载PDF
导出
摘要 钱塘江盾构始发洞门位于淤泥质黏土地层,洞门土体灵敏性高,受到扰动后易发生垮塌涌土与地面沉降,采用深层搅拌桩与高压旋喷桩相结合改良技术可防止该现象的发生。文章介绍了始发井洞门加固方法的选择、深层搅拌桩和高压旋喷桩工艺参数的确定、加固质量控制、洞口井壁混凝土的凿除、加固措施的实施效果等。 The starting hole of shield tunneling at the Qiantanjiang River is located in the silty stratum of high soil sensitivity,where hole collapse,soil gushing and ground settlement are easy to happen while soil is disturbed.The soil reinforcement technique combining deep mixing piles with high pressure jet grouting piles can prevent the starting hole from those damages.This paper presents the method selection of the starting hole reinforcement,process parameter determination of deep mixing piles and high pressure jet grouting piles,reinforcement quality control,cutting away of shaft concrete wall around the starting hole and implementation effects of the reinforcement measures.
出处 《石油工程建设》 2011年第3期63-65,87,共3页 Petroleum Engineering Construction
关键词 盾构始发洞门 淤泥地层 地层加固 深层搅拌桩 高压旋喷桩 starting hole of shield tunneling silty stratum stratum reinforcement deep mixing pile high pressure jet grouting pile
  • 相关文献

同被引文献6

  • 1苏东剑.探讨污水顶管施工技术与质量控制[J].市政工程,2010(23):14.
  • 2王富仁.浅议市政道路排水顶管施工技术[J].科技向导,2011(43):21.
  • 3江东胜.浅谈顶管技术在市政污水管中的应用[J].中国科技博览2011(8):133.
  • 4张凤青.探讨城市污水顶管施工技术要点与控制[J].科技论坛2012(22):60.
  • 5谢石连,郭连江,范利杰.某沉井流砂事故分析与处理[J].地下空间与工程学报,2009,5(3):621-624. 被引量:9
  • 6毛峰.大型污水新老管道改接设计方案分析[J].中国市政工程,2015(1):65-69. 被引量:9

引证文献3

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部