摘要 针对盾构在南京复合地层掘进中,施工参数异常,刀具磨损严重,需要选取围岩条件较好岩层,相当于一个天然加固体,通过先行确立刀具磨损标准、前期技术准备,在常压情况下进仓检查和更换刀具等系列施工技术,确保了作业质量和安全,并使隧道顺利贯通。 In view of the shield-driven tunneling in the Nanjing compound stratum,the construction parameter is unusual,the cutting tool attrition is serious,it needs to select rock layer with good adjacent formation condition,which is equal in a natural reinforcement body.Through the advanced attrition standard,establishment of cutting tool,the preliminary technical preparation,a senies construction technologies,such as inspection of storage and replacement of cutting tool under the normal atmospheric pressure,the construction quality and security have been guarn-teed and the tunneling construction project has been successfully completed.
作者 朱红华
出处 《江苏建筑》 2011年第2期93-96,共4页 Jiangsu Construction
关键词 盾构施工 进仓检查 更换刀具 技术浅析 shield construction places in storage the inspection replaces the cutting tool technical brief analysis
  • 相关文献

参考文献2

  • 1.南京地铁一号线南延线工程XKOI标岔路口站-河定桥站区间岩土工程详细勘察报告[R].,..
  • 2.小松PMD-4改进型单圆质构使用说明书.,..

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部