摘要
南通市海安县人民医院肿瘤治疗中心加速机房2.5 m厚钢筋混凝土现浇板,模板及支架设计采用型钢水平横梁及圆木支撑立柱,解决了厚大体积混凝土模板支架的设计难题,使特殊模板、高支模板的总体施工水平得到了显著的提高。
To improve the overall construction level of the special formwork and highly supported formwork and to solve the design problem of mass concrete formwork support,section steel horizontal beam and log supporting pole is designed for the formwork and supporting system of 2.5m thickness cast –in-situ concrete slab of the accelerator plant room of cancer treatment center in the People's Hospital of Haian County,Nantong City.
出处
《江苏建筑》
2011年第3期45-46,60,共3页
Jiangsu Construction
关键词
加速机房
钢梁
圆木支撑立柱
抗弯强度
挠度
强度
稳定性
accelerator plant room
steel beam
log supporting pole
bending strength
deflection
strength
stability