"十二五"期间,随着山东500kV电网的不断发展完善以及特高压变电站接入山东电网负荷中心,山东500kV系统短路水平将进一步增高;部分变电站500kV母线短路电流超过设备额定遮断容量(50kA),在保证主网架安全可靠运行前提下,对500kV网络进行优化,控制局部500kV变电站的短路水平,是本次研究需要解决的重要问题。
During the next National Twelfth Five-Year Plan period,500kV power grid of shandong province will continuously develop and perfect as well as UHV substation will be built into power grid load center,therefore,500kV system short-circuit current level increased gradually and short-circuit current of 500kV bus in parts of substations exceed rated blocking capacity of circuit breaker.In precondition of guaranteeing the safe and reliable operation of electric wire netting,limitation on short-circuit current level of parts of 500kV substations is important problem to solve in this Study,optimized scheme for Shandong planning Main Network is suggested.
出处
《山东电力高等专科学校学报》
2011年第2期17-19,27,共4页
Journal of Shandong Electric Power College
关键词
电网规划
短路电流
方案优化
power network planning
short-circuit current
scheme optimization