基于现金流均衡目标的多模式项目调度问题研究 被引量:11

Multi-mode Project Scheduling Problems with Cash Flow Balanced Objectives
下载PDF
导出
摘要 首先对基于现金流均衡目标的多模式项目调度问题进行界定;随后定义两组0-1决策变量并构建问题的优化模型;鉴于问题的强NP-hard属性,设计专门的模拟退火启发式算法;最后用一个实例对研究进行说明,并计算分析关键参数对目标函数的影响。结果表明:承包商最大累计资金缺口随项目截止日期的延迟、支付比例和预付款比例的提高而减小,随着质量保证金比例的提高而增大。 A contractor needs to spend capital on project-related resources before receiving payment from customers for services delivered at each milestone.However,contractors have varying capital availabilities when implementing different projects.Thus,balancing cash inflows and outflows throughout the project life cycle is critical to project success for contractors.This paper studies multi-mode project scheduling problems with the goal of balancing cash inflows and outflows.We use the event-based method to represent a contractor's project schedule in the activity-on-node mode,and distribute project expenses to their beginning and ending activities.The objective of this exercise is to minimize the gap of a contractor's cumulative capital flows given the constraint of a fixed project deadline.We define two groups of decision variables in order to determine the modes of performing activities and the actual delivery date of events.A0-1 programming model is established to address cash flow problems.A simulated annealing heuristic algorithm with two nested loops is developed to solve cash flow problems.These two nested loops include inner and outer loops.The inner loop searches for a desirable vector of an event's completion time under a given activity's performing mode.The outer loop seeks the desirable vector of an event's completion time established by the inner loop.The simulation results show desirable solutions for cash problems in innerand outer loops.A contracted superhighway construction project is used as a case study to illustrate the use of our proposed simulated algorithm.This project is able to develop a satisfactory schedule.We compare the developed schedule with the actual schedule regarding key cash flow parameters,including project deadline,payment proportion,advance payment proportion,deposit rate of security payment,and objective function values.A contractor can maximize its cumulative capital gap by reducing the procrastination of project deadline,increasing payment proportion,advancing payment proportion,and increasing deposit rate.The findings of this study can help contractors make better decisions on balancing their cash inflows and outflows,and managing project schedule.
出处 《管理工程学报》 CSSCI 北大核心 2011年第2期124-130,共7页 Journal of Industrial Engineering and Engineering Management
基金 国家自然科学基金资助项目(70971105) 国家社会科学基金资助项目(07XJL002) 陕西省自然科学基金资助项目(2009JM9001) 陕西省科技厅科学计划资助项目(2008RK11)
关键词 现金流均衡 多模式项目调度 优化模型 模拟退火启发式算法 cash flow balance multi-mode project scheduling optimization model simulated annealing heuristic algorithm
  • 相关文献

参考文献20

  • 1Demeulemeester EL, Herroelen WS. Project seheduling--a research handbook [M ]. Boston: Kluwer Academic Publishers, 2002.
  • 2刘士新,王梦光,聂义勇.多执行模式资源受限工程调度问题的优化算法[J].系统工程学报,2001,16(1):55-60. 被引量:24
  • 3Demeulemeester E, Herroelen W. A branch-and-bound procedure for the multiple resource-constrained project scheduling problem [J]. Management Science,1992,38(12) : 1803 - 1818.
  • 4何正文,徐渝,朱少英.Max-npv项目进度问题研究评述[J].管理工程学报,2005,19(4):60-63. 被引量:23
  • 5Yamashita DS, Armentano VA, Laguna M. Scatter search for project scheduling with resource availability cost [ J ]. European Journal of Operational Research,2006,169 : 623 - 637.
  • 6刘士新,王梦光.一种求解工程调度中资源水平问题的遗传算法[J].系统工程理论与实践,2001,21(4):24-26. 被引量:10
  • 7张静文,徐渝,何正文,柴国荣.项目调度中的时间-费用权衡问题研究综述[J].管理工程学报,2007,21(1):92-97. 被引量:24
  • 8Herroelen W, Dommelen V, Demeulemeester E. Project network models with discounted cash flows: a guided tour through recent developments [ J ]. European Journal of Operational Research, 1997,100(1): 97 -121.
  • 9Kolisch R, Padman R. An integrated survey of deterministic project scheduling[ J]. Omega,2001,29(3 ) : 249 - 272.
  • 10Herroelen W, Leus R. Project scheduling under uncertainty: Survey and research potential [ J ]. European Journal of Operational Research ,2005,165 ( 2 ) : 289 - 306.

二级参考文献87

  • 1何正文,徐渝,朱少英.Max-npv项目进度问题研究评述[J].管理工程学报,2005,19(4):60-63. 被引量:23
  • 2何正文,徐渝,朱少英.具有奖励惩罚结构的项目支付进度问题研究:双重角度[J].系统工程理论与实践,2005,25(10):39-45. 被引量:23
  • 3[1]Mo¨hring R H. Minimizing costs of resource requirements in project networks subject to a fixed completion time[J]. Operations Research, 1984, 32: 89-120.
  • 4[2]Bandelloni M, Tucci M, Rinaldi R. Optimal resource levelling using non-serial dynamic programming[J]. European Journal of Operational Research, 1994, 78: 162-177.
  • 5[3]Younis M A, Saad B. Optimal resource levelling of multi-resource projects[J]. Computers and Industrial Engineering, 1996, 31: 1-4.
  • 6[4]Leachman R C. Multiple resource levelling in construction systems through variation of activity intensities[J]. Naval Research Logistics Quarterly, 1983, 30: 187-198.
  • 7[5]Seibert J E, Evans G W. Time-constrained resource levelling[J]. Journal of Construction Engineering and Management, 1991, 117: 503-520.
  • 8[6]Demeulemeester E. Minimizing resource availability costs in time-limited project networks[J]. Management Science, 1995, 41(10): 1590-1598.
  • 9[7]Demeulemeester E, Herroelen W. A branch-and-bound procedure for the multiple resource-constrained project scheduling problem[J]. Management Science, 1992, 38(12): 1803-1818.
  • 10[8]Neumann K, Zimmermann J. Resource levelling for projects with schedule-dependent time windows[J]. European Journal of Operational Research, 1999, 117: 591-605.

共引文献75

同被引文献108

引证文献11

二级引证文献93

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部