摘要
叙述了三峡大江截流实施过程中的施工进度计划、料场规划与土石方平衡、截流方式与围堰断面形式、截流进占程序和时段等主要技术问题的优化完善过程。
This paper describes the process of optimizing and perfecting the major technied pwhlerns such as construction schedule, planning of stocking yard and balance of rock and earth rnaterial, mede of enclosure and type of coverdaxn profile and procedure of advance and time interval during the implementation of TGP's Daiang Closure Work.
出处
《人民珠江》
1999年第6期39-43,共5页
Pearl River
关键词
大江截流
施工方案
方案优化
三峡水利枢纽
encloure of Dajiang construction scheme optimization of scheme Three Gorges Project (TGP)