摘要 码头施工中,由于受地质因素影响,岩层上覆盖层较薄,在其结构选型上,多采用嵌岩灌注桩。嵌岩灌注桩岩层的确定,是设计、施工、监理等各方均非常关注的核心问题。嵌岩灌注桩施工中如何确定中等风化岩层和微风化岩层的高程,如何准确地判定其岩性,成为当前迫切的任务。阐述嵌岩灌注桩施工中,经常遇到的岩层确定问题,提出了对策并成功应用于实际工程。 In wharf construction,since the covering layer of strata is very thin due to the affection from its surrounding geologic condition,the rock-socketed filling pile has been widely applied.The judgement of the terrane's quality of rock-socketed filling pile is the key in the design,construction and supervision.This paper expounds the judgement of the terrane's quality during constrution of rock-socketed filling piles,and proposes countermeasures which have been applied to the real project.
作者 余敏
出处 《水运工程》 北大核心 2011年第6期164-166,共3页 Port & Waterway Engineering
关键词 嵌岩灌注桩 岩层确定 对策 rock-socketed filling pile terrane determination countermeasure
  • 相关文献

参考文献4

  • 1JTJ285--2000.港口工程嵌岩桩设计与施工规程[S].[S].,..
  • 2JTJ248--2001港口工程灌注桩设计与施工规程[S].
  • 3JGJ1994--1994建筑桩基技术规范[S].
  • 4中交水运规划设计院有限公司.重庆主城港区东港作业区一期工程初步设计[R].北京:中交水运规划设计院有限公司.2009.

共引文献6

同被引文献4

  • 1JTS167-4-2012.港口工程桩基规范[S].
  • 2黄汉明.锚杆嵌岩桩在港口工程中的应用[J].江苏交通科技,2009,(7):124--127.
  • 3JTS167-1-2011,高桩码头设计与施工规范[S].
  • 4朱成.海洋码头工程嵌岩桩施工[J].江苏交通科技,2010(4):32-34. 被引量:1