摘要
大庙水利枢纽坝址位于陡峻"V型"河谷中,两岸基岩出露,根据河谷的形状特征和地形、地质条件,进行坝型方案布置和技术经济比较,最终选择上坝线砼双曲拱坝方案。
Damiao Hydraulic Complex is located at a V-shape steep river valley with base rock exposed on both banks. According to the shape, the topographical and geological conditions of river valley, the technical and economic indexes of various dam type schemes were compared, based on which the scheme of double-curvature arch dam arranged at upper dam axis was selected
出处
《广西水利水电》
2011年第3期13-15,21,共4页
Guangxi Water Resources & Hydropower Engineering
关键词
水利枢纽
拦河坝
坝型
双曲拱坝
Hydraulic complex
water retaining dam
dam type
double-curvature arch dam