关于阴极保护标准及工程测量方法的探讨 被引量:1

Study on Cathodic Protection Standard and Engineering Measurement
下载PDF
导出
摘要 研究表明,在阴极保护实际工程应用中,传统的通电12 s后断电3 s的测量方法并不能得到准确的断电电位数据。IR降的正确测量可以通过专业仪器得到,也可在工程现场用万用表进行简单测量后进行修正得到。另外,在正常情况下,-100 mV极化可以将电化学腐蚀速率降低到原来的2%;极端情况下也可以降低到原来的1/7。因此应该重视-100 mV的极化标准,并将此准则同样视为阴极保护工程验收的一条重要标准。 The research has shown that, in project application of cathodic protection, the accurate electric potential data can not be got by conventional measures, i.e. measurement after power on for 12 s and power off for 3 s. The correct measurement of IR drop can be obtained by special instrument or by universal meter after correction. In normal conditions, - 100 mY polarization can reduce the electro - chemical corrosion rate to 2% of the original and 1/7 of the original in extreme case. Great attention shall be paid to - 100 mV polarization standard, which shall be regarded as an important standard in the inspection and acceptanee of cathodic protection project.
出处 《石油化工腐蚀与防护》 CAS 2011年第3期25-27,共3页 Corrosion & Protection In Petrochemical Industry
关键词 阴极保护 IR降 断电测试 保护电位B值 cathodic protection, IR drop, power - off testing, protection electric potential, B value
  • 相关文献

参考文献2

  • 1曹楚南.腐蚀电化学[M].北京:化学工业出版社,1994.131.
  • 2H.H.尤里克.腐蚀与腐蚀控制[M].北京:石油工业出版社,1985:62.

共引文献148

同被引文献3

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部