摘要
介绍了二龙山水库冲沙泄洪底孔进口检修闸门和工作闸门,在运行28 a之后,对冲沙泄洪底孔进口检修闸门、工作闸门和启闭设备进行重新设计、制造及更换后的闸门和启闭机设备经数十年的运行、维护等情况。
The paper describes the decades of operation and maintenance of the emergency gate,working gate and hoisting equipment at the inlet of the flood-discharge and sand-sluicing bottom outlet of the Erlongshan reservoir after they were redesigned,manufactured and replaced following 28 years of operation.
出处
《西北水电》
2011年第3期80-81,共2页
Northwest Hydropower
关键词
冲沙泄洪底孔
检修闸门
工作闸门
启闭机
更换
flood-discharge and sand-sluicing bottom outlet
emergency gate
working gate
hoist