摘要
针对广东省罗定市城区"十二五"期间供电负荷进行了预测,根据预测结果,结合市政规划对该城区高压变电站的位置进行了规划及校验,以验证变电站的合理性,提出在现有双东变电站附近新建一变电站,以缓解其供电压力。
The paper forecasts the power loading in Luoding city of Guangdong during "The Twelfth Five-year" period, has the planning and in- spection for the location of the high-voltage substation in the districts combining with the municipal planning according to the forecasting results to prove the reasonability of the substation, and points out the newly-built substation near the current Shuangdong substation, so as to relieve the power pressure
出处
《山西建筑》
2011年第21期116-117,共2页
Shanxi Architecture
关键词
供电负荷
预测方法
分区负荷
高压变电站
power loading, forecasting method, subarea loading, high-voltage substation