随着高强度绝缘绳的出现,利用铁塔作为支撑体的无跨越架不停电封网跨越技术得到了推广应用。本文结合工程实例针对该类施工过程中监理需在现场着重控制点进行了论述。
With the emergence of high strength insulation wire,crossing technology on Live-lines without Crossing Structure obtained the widespread application.Tower is used as supporting body.According to concrete engineering examples,the authors discuss supervision control points on scene in this kind of construction process.
出处
《粮食流通技术》
2011年第2期13-14,40,共3页
Grain Distribution Technology
关键词
无跨越架
不停电
监理控制点
Without acrossing frame
Live-lines
Supervision control points